Hazard: SY4 core switch upgrades
Scheduled Maintenance Report for Intergrid
Completed
The maintenance work has been completed without customer impact.
Posted Apr 21, 2019 - 11:31 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 21, 2019 - 10:00 AEST
Scheduled
Following a service degradation incident impacting several customers on the 10th of April, network technicians will be upgrading and replacing core switches on our SY4 network. During the works, switching equipment susceptible to a vendor firmware bug will be replaced.

This is a hazard notice only. Upgrades will be carried out on one core switch at a time. Due to the redundancy of the SY4 core network, no customer impact is expected. However, customers are advised that the Sydney network will be running with reduced redundancy and capacity during the works. There may be a 3 to 5 minute period of minor packet loss and/or service degradation while routes re-converge to the new equipment.

We recognise the impact of any scheduled works on customers, and this essential upgrade has been scheduled on a public holiday to minimise any unforeseen impact. If you have any questions prior to or during this maintenance window, please contact the Service Desk at support@intergrid.com.au referencing event number SY4-3930.
Posted Apr 13, 2019 - 10:15 AEST
This scheduled maintenance affected: Sydney - Equinix SY3/SY4 (Dedicated servers, Virtual servers, Network & IP transit).