Scheduled maintenance - Melbourne [1/2]
Scheduled Maintenance Report for Intergrid
Completed
The scheduled maintenance has been completed.
Posted Dec 12, 2020 - 10:00 AEDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 12, 2020 - 06:01 AEDT
Scheduled
On the morning of Saturday 12 December and Sunday 13 December, Intergrid technicians will be relocating certain servers from older datacentre facilities to our new Melbourne network. This work is necessary to improve the security, performance, and reliability of services.

During the maintenance window, services are expected to be impacted for 60-90 minutes while they are relocated. As this work does not impact all customers, those affected have been contacted directly through a personalised maintenance notification.
Posted Dec 04, 2020 - 08:00 AEDT
This scheduled maintenance affected: Melbourne - Equinix ME1 (Dedicated servers, Virtual servers).