Intergrid will be performing network upgrades in our Auckland datacentre on Friday 1st June 2018, from 5PM local time. The works will involve upgrading uplinks to rack switches, upgrading some core routing equipment and provisioning additional peering capacity. Due to the redundant nature of our network, no customer impact is expected. However, there may be up to 3 periods of 4-5 minutes of service degradation for Auckland servers and colocation while routes re-converge. Updates will be posted on this status page as required during the maintenance period. If you have any questions about this maintenance, please contact the Intergrid Service Desk at